SOLAR Β· MISO

Solar project J2225, Henderson County

Solar project J2225, Henderson County is a 300 MW solar request withdrawn in the MISO interconnection queue, in Henderson County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2225
Grid region
MISO (Midcontinent)
Utility / transmission owner
BIG RIVERS ELECTRIC CORPORATION
Connection point (POI)
REID EHV 345 KV SUBSTATION
Location
Henderson County, Kentucky
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
17 August 2021
Proposed online date
April 2025

Location

Marker shows the centre of Henderson County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Henderson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem