United States › Grid › Interconnection queues › Kentucky
SOLAR · MISOSolar project J1466, Henderson County
Solar project J1466, Henderson County is a 250 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Henderson County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedMay 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Aug 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1466
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- BIG RIVERS ELECTRIC CORPORATION
- Connection point (POI)
- Reid EHV 161 kV Substation
- Location
- Henderson County, Kentucky
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 23 May 2023
- Proposed online date
- August 2025
Location
Marker shows the centre of Henderson County; the queue data does not give exact sites.
Other requests in Henderson County
- Solar project J2931, Henderson CountySolar · 400 MW · in study
- Onshore wind project J2930, Henderson CountyOnshore wind · 200 MW · in study
- Battery storage project J2844, Henderson CountyBattery storage · 200 MW · in study
- Solar project J1696, Henderson CountySolar · 150 MW · in study
- Solar project J1604, Henderson CountySolar · 50.0 MW · in study
- Other project G108, Henderson CountyOther · 1,000 MW · withdrawn
- Gas project LGE-GIS-2007-004, Henderson CountyGas · 642 MW · withdrawn
- Coal project J237, Henderson CountyCoal · 642 MW · withdrawn
- Gas project LGE-GIS-2007-003, Henderson CountyGas · 640 MW · withdrawn
- Coal project R44, Henderson CountyCoal · 485 MW · withdrawn
- Solar project J1886, Henderson CountySolar · 300 MW · withdrawn
- Solar project J2225, Henderson CountySolar · 300 MW · withdrawn