Solar project J3959, Grundy County

Solar project J3959, Grundy County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Grundy County, Missouri, connecting to AMEREN MISSOURI.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3959
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
Other_
Location
Grundy County, Missouri
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
17 April 2025
Proposed online date
November 2029

Location

Marker shows the centre of Grundy County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri