Interconnection queue in the USA — page 52

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 52 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J4001, Marion County
Solar
245 MWIn study Marion, MOMISO Apr 2025target 2030
Solar project J3949, Scott County
Solar
245 MWIn study Scott, ILMISO Apr 2025target 2030
Solar project J4148, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Solar project J2849, Pulaski County
Solar
245 MWIn study Pulaski, INMISO Sep 2022target 2025
Solar project J3961, Lincoln County
Solar
245 MWIn study Lincoln, MNMISO Apr 2025target 2030
Eastbell Milam Solar
Solar · EDP RENEWABLES NORTH AMERICA LLC
245 MWAgreement signed Milam, TXERCOT Oct 2018target 2025
Gail Mountain Solar
Solar · Gail Mountain Solar, LLC
244 MWIn study Borden, TXERCOT Oct 2024target 2028
Solar project J2870, Sawyer County
Solar
244 MWIn study Sawyer, WIMISO Sep 2022target 2026
Lavaca Bay Solar
Solar · Lavaca Bay Solar Project, LLC
244 MWAgreement signed Matagorda, TXERCOT Sep 2020target 2026
Brazos Bend Solar SLF
Solar + storage · Grenergy USA
243 MWIn study Milam, TXERCOT Sep 2025target 2029
Brazos Bend Storage SLF
Solar + storage · Grenergy USA
243 MWIn study Milam, TXERCOT Sep 2025target 2029
Coyote Wind
Onshore wind · Coyote Wind
243 MWAgreement signed Scurry, TXERCOT Apr 20152021
Onshore wind project Q458, Navajo County
Onshore wind
242 MWIn study Navajo, AZWest Mar 2022target 2026
Lupinus Solar 2
Solar + storage · Lupinus Solar 2, LLC
242 MWAgreement signed Franklin, TXERCOT Dec 2021target 2027
Solar project GEN-2017-141, Wagoner County
Solar
242 MWAgreement signed Wagoner, OKSPP Nov 2017target 2027
Lutum Wind
Onshore wind · RWE
242 MWIn study Clay, TXERCOT Sep 2017target 2027
Diaz BESS
Battery storage · BRP Blue Topaz 10, LLC
242 MWIn study Cameron, TXERCOT May 2023target 2027
Onshore wind project GEN-2024-236, Okfuskee County
Onshore wind
241 MWIn study Okfuskee, OKSPP Mar 2025target 2029
Best Southwest BESS
Battery storage
241 MWPaused / redesign Dallas, TXERCOT May 2022target 2025
Peyton Creek Wind II
Onshore wind · RWE Renewables Development, LLC
241 MWAgreement signed Matagorda, TXERCOT Aug 2018target 2026
Easy Wind Energy Center
Wind + storage · Easy Wind Energy Center, LLC
241 MWIn study Schleicher, TXERCOT May 2024target 2027
Duffy BESS
Solar + storage · Duffy Energy Storage LLC
241 MWAgreement signed Matagorda, TXERCOT Aug 2023target 2026
Other project 98, Pinal County
Other
241 MWIn study Pinal, AZWest Sep 2021target 2025
Jane Storage Energy Center
Battery storage · NMRE Holdings, LLC
241 MWIn study Martin, TXERCOT Sep 2023target 2027
Giddings Wind
Onshore wind · Pioneer Natural Resources
240 MWIn study Upton, TXERCOT Sep 2017target 2030
Solar + storage project 605, Elmore County
Solar + storage · South Bennett Solar LLC
240 MWPaused / redesign Elmore, IDWest May 2021target 2029
Solar project GI-2019-6, Pueblo County
Solar
240 MWIn study Pueblo, COWest May 20192021
Battery storage project J4117, Goodhue County
Battery storage
240 MWIn study Goodhue, MNMISO Sep 2025target 2030
Solar + storage project Company QX, Churchill County
Solar + storage
240 MWIn study Churchill, NVWest Mar 2024target 2028
Solar project S0004, Carbon County
Solar · PacifiCorp
240 MWIn study Carbon, WYWest Mar 2022target 2026
Solar + storage project 551, Elmore County
Solar + storage · Bennett Solar B LLC
240 MWPaused / redesign Elmore, IDWest Apr 2019target 2026
Thundering Springs
Solar + storage
240 MWIn study Laurens, GASoutheast Nov 20192023
Bob Creek Wind
Onshore wind · NextEra Energy Interconnection Holdings, LLC
240 MWAgreement signed Sterling, TXERCOT Jan 2024target 2028
Town Line Solar CSR Phase I
Solar + storage · RWE Solar Development, LLC
240 MWIn study Sullivan, NYNYISO Oct 2024target 2030
Gas project 25-IC-1320A, Lee County
Gas
240 MWIn study Lee, ALSoutheast Apr 2025target 2029
Solar + storage project J3985, Polk County
Solar + storage
240 MWIn study Polk, TXMISO Nov 2024target 2030
Cadence Solar Energy Center
Solar
240 MWAgreement signed Union, OHPJM Mar 2018target 2026
Windstar I Alternate
Wind + storage
240 MWAgreement signed Kern, CACAISO Apr 20062012
Solar project J1067, Jasper County
Solar
240 MWUnder construction Jasper, INMISO Mar 20182024
Battery storage project J2567, Oceana County
Battery storage
240 MWIn study Oceana, MIMISO Sep 2022target 2025
Razorbill Solar
Solar + storage · RWE Solar Development, LLC
240 MWIn study Matagorda, TXERCOT Jan 2020target 2027
Rich Road Solar Energy Center
Solar + storage · Rich Road Solar Energy Center, LLC
240 MWIn study St. Lawrence, NYNYISO Feb 2019target 2028
Solar project J2149, Saline County
Solar
240 MWIn study Saline, ARMISO Nov 2021target 2024
Solar + storage project Company HQ, Pershing County
Solar + storage
240 MWPaused / redesign Pershing, NVWest Sep 2017target 2024
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
Midway Peaking
Gas
240 MWAgreement signed Fresno, CACAISO Jan 20052009
Gas project GEN-2023-223, Gage County
Gas
239 MWIn study Gage, NESPP Oct 2023target 2030
Solar project GEN-2022-214, Sumner County
Solar
239 MWIn study Sumner, KSSPP Mar 2023target 2028
Onshore wind project G0640, Klamath County
Onshore wind
239 MWIn study Klamath, ORWest Feb 2020target 2025
Camino Ranch Storage 2 SLF
Solar + storage · Camino Ranch Solar LLC
239 MWIn study Houston, TXERCOT Feb 2024target 2028
Page 52 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)