ONSHORE WIND · ERCOT

Bob Creek Wind

Bob Creek Wind is a 240 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Sterling County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2024 (completed)
  2. ConsentedJun 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
27INR0076
Grid region
ERCOT (Texas)
Developer
NextEra Energy Interconnection Holdings, LLC
Connection point (POI)
59902 Sand Bluff 345kV
Location
Sterling County, Texas
Technology
Wind: 240 MW
Total requested
240 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
11 January 2024
Agreement signed
6 June 2025
Proposed online date
July 2028

Location

Marker shows the centre of Sterling County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Sterling County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem