United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTBob Creek Wind
Bob Creek Wind is a 240 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Sterling County, Texas.
Queue statusConsented
- PlanningQueued Jan 2024 (completed)
- ConsentedJun 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 27INR0076
- Grid region
- ERCOT (Texas)
- Developer
- NextEra Energy Interconnection Holdings, LLC
- Connection point (POI)
- 59902 Sand Bluff 345kV
- Location
- Sterling County, Texas
- Technology
- Wind: 240 MW
- Total requested
- 240 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 11 January 2024
- Agreement signed
- 6 June 2025
- Proposed online date
- July 2028
Location
Marker shows the centre of Sterling County; the queue data does not give exact sites.
Other requests in Sterling County
- Capricorn I & III repowerOnshore wind · 32.0 MW · agreement signed
- Goat Mountain Wind-RepowerWind + storage · 303 MW · in study
- Roan Solar Phase 1Solar · 206 MW · in study
- Roan Solar Phase 2Solar · 206 MW · in study
- Goat Mountain BESSWind + storage · 201 MW · in study
- Goat Mountain BESS 2Wind + storage · 101 MW · in study
- BlueBell Solar IISolar · 115 MW · built
- Capricorn IV repowerOnshore wind · 9.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem