United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

BlueBell Solar II

BlueBell Solar II is a 115 MW solar request built and operating in the ERCOT interconnection queue, in Sterling County, Texas.

Queue statusOperating
  1. PlanningQueued Oct 2018 (completed)
  2. ConsentedMar 2020 (completed)
  3. Construction (completed)
  4. OperatingApr 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0204
Grid region
ERCOT (Texas)
Developer
Bluebell Solar
Connection point (POI)
76090 Divide 345kV
Location
Sterling County, Texas
Technology
Solar: 115 MW
Total requested
115 MW
Study phase
IA
Queue status
Operational
Entered queue
22 October 2018
Agreement signed
12 March 2020
Proposed online date
June 2021
Came online
April 2021

Location

Marker shows the centre of Sterling County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Sterling County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem