United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTBlueBell Solar II
BlueBell Solar II is a 115 MW solar request built and operating in the ERCOT interconnection queue, in Sterling County, Texas.
Request details
- Queue ID
- 20INR0204
- Grid region
- ERCOT (Texas)
- Developer
- Bluebell Solar
- Connection point (POI)
- 76090 Divide 345kV
- Location
- Sterling County, Texas
- Technology
- Solar: 115 MW
- Total requested
- 115 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 22 October 2018
- Agreement signed
- 12 March 2020
- Proposed online date
- June 2021
- Came online
- April 2021
Location
Marker shows the centre of Sterling County; the queue data does not give exact sites.
Other requests in Sterling County
- Bob Creek WindOnshore wind · 240 MW · agreement signed
- Capricorn I & III repowerOnshore wind · 32.0 MW · agreement signed
- Goat Mountain Wind-RepowerWind + storage · 303 MW · in study
- Roan Solar Phase 1Solar · 206 MW · in study
- Roan Solar Phase 2Solar · 206 MW · in study
- Goat Mountain BESSWind + storage · 201 MW · in study
- Goat Mountain BESS 2Wind + storage · 101 MW · in study
- Capricorn IV repowerOnshore wind · 9.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem