SOLAR · SPPSolar project GEN-2017-141, Wagoner County
Solar project GEN-2017-141, Wagoner County is a 242 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Wagoner County, Oklahoma, connecting to AEP.
Queue statusConsented
- PlanningQueued Nov 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2017-141
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Clarksville 345kV Switching Station
- Location
- Wagoner County, Oklahoma
- Technology
- Solar: 242 MW
- Total requested
- 242 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 22 November 2017
- Proposed online date
- December 2027
Location
Marker shows the centre of Wagoner County; the queue data does not give exact sites.
Other requests in Wagoner County
- Solar project GEN-2017-140, Wagoner CountySolar · 160 MW · agreement signed
- Battery storage project GEN-2024-118, Wagoner CountyBattery storage · 199 MW · in study
- Solar project GEN-2017-180, Wagoner CountySolar · 250 MW · withdrawn
- Onshore wind project GEN-2017-122, Wagoner CountyOnshore wind · 234 MW · withdrawn
- Onshore wind project GEN-2017-143, Wagoner CountyOnshore wind · 227 MW · withdrawn
- Onshore wind project GEN-2017-129, Wagoner CountyOnshore wind · 222 MW · withdrawn
- Battery storage project GEN-2017-170, Wagoner CountyBattery storage · 52.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem