Interconnection queue in the USA — page 41

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 41 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Vista Bluff Wind I "Alternate POI"
Onshore wind · Vista Bluff Windpower, LLC
290 MWIn study Upton, TXERCOT Sep 2025target 2029
Tres Rios Ranch BESS
Solar + storage · LectricWind LLC
290 MWIn study Upton, TXERCOT May 2023target 2027
Solar project AI1-085, Wayne County
Solar
290 MWIn study Wayne, INPJM Jul 2022target 2030
Solar project AH2-322, Pittsylvania County
Solar
290 MWIn study Pittsylvania, VAPJM Mar 2022target 2025
Onshore wind project G0761, Grant County
Onshore wind
290 MWIn study Grant, WAWest Jun 2022target 2026
Onshore wind project BHBE G16, Campbell County
Onshore wind
290 MWAgreement signed Campbell, WYWest Dec 2021target 2024
Battery Storage
Battery storage
290 MWIn study Berkshire, MAISO-NE Apr 2024target 2028
Solar project J3274, Ogemaw County
Solar
290 MWIn study Ogemaw, MIMISO Apr 2024target 2028
Onshore wind project J4006, Ringgold County
Onshore wind
290 MWIn study Ringgold, IAMISO May 2025target 2030
Shifting Gale Wind
Onshore wind
289 MWPaused / redesign Castro, TXERCOT Apr 2018target 2025
Onshore wind project J3902, Jefferson County
Onshore wind
289 MWIn study Jefferson, TXMISO Feb 2025target 2028
Solar project GEN-2022-016, Woodward County
Solar
288 MWIn study Woodward, OKSPP Jun 2022target 2028
Solar + storage project J3002, Pine County
Solar + storage
288 MWIn study Pine, MNMISO Sep 2022target 2025
Sandow Solar
Solar · Sandow Lakes Ranch Solar I, LLC
287 MWIn study Milam, TXERCOT Sep 2020target 2028
Baker Branch BESS
Battery storage · Mockingbird Storage Center, LLC
287 MWIn study Lamar, TXERCOT Jun 2025target 2029
Inadale BESS
Solar + storage · Inadale BESS, LLC
287 MWIn study Scurry, TXERCOT Feb 2023target 2028
Solar project J3012, Coles County
Solar
287 MWIn study Coles, ILMISO Sep 2022target 2026
Gas project G1008, Clark County
Gas
286 MWIn study Clark, WAWest Nov 2023target 2024
Spindletop Solar
Solar + storage · Banita Creek Solar LLC
286 MWAgreement signed Nacogdoches, TXERCOT Jul 2024target 2027
Fierce River BESS
Solar + storage · Rio Grande Solar LLC
285 MWIn study Starr, TXERCOT Mar 2024target 2029
Monarch Creek Wind
Onshore wind · MONARCH CREEK WIND, LLC
284 MWAgreement signed Throckmorton, TXERCOT Apr 2019target 2027
Fivemile Wind
Onshore wind · Longview Wind, LLC
282 MWIn study Dawson, TXERCOT Apr 2025target 2028
Impala Flats Wind
Onshore wind · Antelope Flats Wind, LLC
282 MWIn study Lynn, TXERCOT Jan 2019target 2026
Treehouse Solar
Solar + storage · Treehouse Solar, LLC
282 MWIn study Grimes, TXERCOT Jul 2025target 2028
Piedra Solar
Solar + storage · Piedra Solar, LLC
282 MWAgreement signed Freestone, TXERCOT Sep 2022target 2026
Jukebox Solar
Solar · ACE DevCo NC, LLC
281 MWIn study Frio, TXERCOT Jun 2025target 2027
Inadale Solar
Solar + storage · Inadale Solar, LLC
281 MWIn study Scurry, TXERCOT Feb 2023target 2028
Battery storage project AI1-187, Hunterdon County
Battery storage
280 MWIn study Hunterdon, NJPJM Sep 2022target 2027
Wright Solar
Solar + storage
280 MWAgreement signed Merced, CACAISO Mar 2011target 2026
Battery storage project GEN-2024-170, Cass County
Battery storage
280 MWIn study Cass, MOSPP Mar 2025target 2028
Solar project J3014, Rapides Parish County
Solar
280 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Solar project AG2-453, Kendall County
Solar · Fox Valley Energy Facility, LLC
280 MWIn study Kendall, ILPJM Feb 2025target 2024
Solar project 737, Bingham County
Solar
280 MWIn study Bingham, IDWest Sep 2023target 2027
Onshore wind project 719, Albany County
Onshore wind · Two Rivers Wind, LLC
280 MWPaused / redesign Albany, WYWest Nov 2015target 2024
Excelsior Energy Center
Solar · Excelsior Energy Center, LLC
280 MWIn study Genesee, NYNYISO Jun 2018target 2026
Solar project AH2-342, Stark County
Solar
280 MWIn study Stark, ILPJM Mar 2022target 2027
Solar + storage project GEN-2024-015, Yoakum County
Solar + storage
280 MWIn study Yoakum, TXSPP Oct 2024target 2028
Battery storage project G0724, Curry County
Battery storage
280 MWIn study Curry, ORWest Jan 2022target 2026
Sandcut Storage
Solar + storage · Hoosier Energy / Solvenz
280 MWIn study Vigo, INMISO Dec 2025target 2028
Unicorn BESS
Battery storage · Unicorn Energies
279 MWIn study Fort Bend, TXERCOT Jan 2024target 2027
Onshore wind project G0994, Sherman County
Onshore wind
277 MWIn study Sherman, ORWest Nov 2023target 2028
Crossroads Wind
Onshore wind · HyFuels Green Lake Wind LLC
277 MWAgreement signed Victoria, TXERCOT Sep 2022target 2027
Pease River Solar
Solar · Pease River Solar LLC
276 MWIn study Foard, TXERCOT Dec 2025target 2029
Blue Hills Wind
Onshore wind
276 MWPaused / redesign Val Verde, TXERCOT May 2019target 2026
Gas project 636, Humphreys County
Gas
276 MWIn study Humphreys, TNSoutheast Jul 2024target 2028
Solar + storage project PIS047, Juab County
Solar + storage
275 MWIn study Juab, UTWest Dec 2023target 2027
Solar project J813, Clay County
Solar
275 MWUnder construction Clay, ILMISO Jun 20172024
Solar project 923973, Richmond County
Solar · Masked
275 MWIn study Richmond, NCSoutheast Sep 2023
Other project Q582, Maricopa County
Other
275 MWIn study Maricopa, AZWest May 2025target 2030
Other project PP00046, Richmond County
Other
275 MWIn study Richmond, NCSoutheast Aug 2025target 2029
Page 41 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)