United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTSpindletop Solar
Spindletop Solar is a 286 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Nacogdoches County, Texas.
Queue statusConsented
- PlanningQueued Jul 2024 (completed)
- ConsentedDec 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 27INR0313
- Grid region
- ERCOT (Texas)
- Developer
- Banita Creek Solar LLC
- Connection point (POI)
- Tap Stryker [3109] - Lufkin [3117] 345 kV line
- Location
- Nacogdoches County, Texas
- Technology
- Solar: 286 MW · Battery
- Total requested
- 286 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 30 July 2024
- Agreement signed
- 29 December 2025
- Proposed online date
- June 2027
Location
Marker shows the centre of Nacogdoches County; the queue data does not give exact sites.
Other requests in Nacogdoches County
- Middlebrook Solar Limited Liability CompanySolar + storage · 316 MW · agreement signed
- Middlebrook BESSSolar + storage · 159 MW · agreement signed
- Spindletop StorageSolar + storage · 143 MW · agreement signed
- Sunlit Pines BESS SLFSolar + storage · 208 MW · in study
- Sunlit Pines Solar SLFSolar + storage · 207 MW · in study
- Timberline SolarSolar + storage · 201 MW · in study
- Timberline StorageSolar + storage · 101 MW · in study
- Gas project GEN-2014-018, Nacogdoches CountyGas · 757 MW · withdrawn
- Gas project GEN-2014-017, Nacogdoches CountyGas · 477 MW · withdrawn
- Gas project GEN-2014-016, Nacogdoches CountyGas · 227 MW · withdrawn
- Gas project GEN-2001-034, Nacogdoches CountyGas · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem