SOLAR + STORAGE · ERCOT

Middlebrook BESS

Middlebrook BESS is a 159 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Nacogdoches County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2022 (completed)
  2. ConsentedJul 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0215
Grid region
ERCOT (Texas)
Developer
Middlebrook Solar LLC
Connection point (POI)
Tap 345kV 3109 Stryker - 3117 Lufkin
Location
Nacogdoches County, Texas
Technology
Battery: 159 MW · Battery
Total requested
159 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
24 October 2022
Agreement signed
21 July 2025
Proposed online date
June 2027

Location

Marker shows the centre of Nacogdoches County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Nacogdoches County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem