🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Sunlit Pines BESS SLF

Sunlit Pines BESS SLF is a 208 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Nacogdoches County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0228
Grid region
ERCOT (Texas)
Developer
Sunlit Pines BESS LLC
Connection point (POI)
Tap 138 kV 3342 Bayou Loco - 3341 Central Angelina County
Location
Nacogdoches County, Texas
Technology
Battery: 208 MW · Battery
Total requested
208 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
9 April 2024
Proposed online date
October 2027

Location

Marker shows the centre of Nacogdoches County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Nacogdoches County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem