United States › Grid › Interconnection queues › Illinois

SOLAR · PJM

Solar project AG2-453, Kendall County

Solar project AG2-453, Kendall County is a 280 MW solar request in interconnection study in the PJM interconnection queue, in Kendall County, Illinois, connecting to ComEd.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-453
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Developer
Fox Valley Energy Facility, LLC
Connection point (POI)
Lasalle - Plano 345 kV
Location
Kendall County, Illinois
Technology
Solar: 280 MW
Total requested
280 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
7 February 2025
Proposed online date
March 2024

Location

Marker shows the centre of Kendall County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Kendall County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem