United States › Grid › Interconnection queues › Illinois
SOLAR + STORAGE · PJMSolar + storage project AH2-258, Kendall County
Solar + storage project AH2-258, Kendall County is a 172 MW solar + storage request in interconnection study in the PJM interconnection queue, in Kendall County, Illinois, connecting to ComEd.
Queue statusIn planning
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-258
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Plano 345 kV
- Location
- Kendall County, Illinois
- Technology
- Solar: 172 MW · Battery
- Total requested
- 172 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 9 March 2022
- Proposed online date
- September 2024
Location
Marker shows the centre of Kendall County; the queue data does not give exact sites.
Other requests in Kendall County
- Solar project AG2-453, Kendall CountySolar · 280 MW · in study
- Battery storage project AH2-259, Kendall CountyBattery storage · 172 MW · in study
- Plano Skies Energy CenterSolar · 150 MW · in study
- Plano Skies Energy CenterSolar · 100 MW · in study
- Solar project AI1-119, Kendall CountySolar · 28.8 MW · in study
- Gas project V1-022, Kendall CountyGas · 380 MW · withdrawn
- Battery storage project AE2-340, Kendall CountyBattery storage · 209 MW · withdrawn
- Gas project AB2-154, Kendall CountyGas · 65.0 MW · withdrawn
- Battery storage project AF2-329, Kendall CountyBattery storage · 42.2 MW · withdrawn
- Solar + storage project AF2-034, Kendall CountySolar + storage · 20.0 MW · withdrawn
- Gas project AA2-136, Kendall CountyGas · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem