United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTPease River Solar
Pease River Solar is a 276 MW solar request in interconnection study in the ERCOT interconnection queue, in Foard County, Texas.
Queue statusIn planning
- PlanningQueued Dec 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0476
- Grid region
- ERCOT (Texas)
- Developer
- Pease River Solar LLC
- Connection point (POI)
- Tap 345kV 6101 RILEY7A - 60505 EDITHCLA7B
- Location
- Foard County, Texas
- Technology
- Solar: 276 MW
- Total requested
- 276 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 2 December 2025
- Proposed online date
- June 2029
Location
Marker shows the centre of Foard County; the queue data does not give exact sites.
Other requests in Foard County
- Seine BESSBattery storage · 301 MW · agreement signed
- Foard City WindOnshore wind · 350 MW · built
- Montgomery Ranch WindOnshore wind · 200 MW · built
- Solar project GEN-2018-092, Foard CountySolar · 400 MW · withdrawn
- Solar project GEN-2022-244, Foard CountySolar · 200 MW · withdrawn
- Solar project GEN-2022-243, Foard CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem