ONSHORE WIND · ERCOTFoard City Wind
Foard City Wind is a 350 MW onshore wind request built and operating in the ERCOT interconnection queue, in Foard County, Texas.
Request details
- Queue ID
- 19INR0019
- Grid region
- ERCOT (Texas)
- Developer
- Innergex
- Connection point (POI)
- 60500 Edith Clarke 345kV
- Location
- Foard County, Texas
- Technology
- Wind: 350 MW
- Total requested
- 350 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 18 October 2016
- Agreement signed
- 6 November 2018
- Proposed online date
- December 2019
- Came online
- December 2019
Location
Marker shows the centre of Foard County; the queue data does not give exact sites.
Other requests in Foard County
- Seine BESSBattery storage · 301 MW · agreement signed
- Pease River SolarSolar · 276 MW · in study
- Montgomery Ranch WindOnshore wind · 200 MW · built
- Solar project GEN-2018-092, Foard CountySolar · 400 MW · withdrawn
- Solar project GEN-2022-244, Foard CountySolar · 200 MW · withdrawn
- Solar project GEN-2022-243, Foard CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem