ONSHORE WIND · ERCOT

Montgomery Ranch Wind

Montgomery Ranch Wind is a 200 MW onshore wind request built and operating in the ERCOT interconnection queue, in Foard County, Texas.

Queue statusOperating
  1. PlanningQueued Dec 2017 (completed)
  2. ConsentedMar 2022 (completed)
  3. Construction (completed)
  4. OperatingDec 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0040
Grid region
ERCOT (Texas)
Developer
RWE Renewables Development, LLC
Connection point (POI)
tap 345kV 60500 Edith Clark – 60506 Avogrado
Location
Foard County, Texas
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
IA
Queue status
Operational
Entered queue
17 December 2017
Agreement signed
22 March 2022
Proposed online date
March 2025
Came online
December 2024

Location

Marker shows the centre of Foard County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Foard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem