United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· SPPSolar project GEN-2022-243, Foard County
Solar project GEN-2022-243, Foard County is a 200 MW solar request withdrawn in the SPP interconnection queue, in Foard County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-243
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Oklaunion-Tuco 345kV Line Break
- Location
- Foard County, Texas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 10 March 2023
- Proposed online date
- December 2027
- Withdrawn
- November 2023
Location
Marker shows the centre of Foard County; the queue data does not give exact sites.
Other requests in Foard County
- Seine BESSBattery storage Β· 301 MW Β· agreement signed
- Pease River SolarSolar Β· 276 MW Β· in study
- Foard City WindOnshore wind Β· 350 MW Β· built
- Montgomery Ranch WindOnshore wind Β· 200 MW Β· built
- Solar project GEN-2018-092, Foard CountySolar Β· 400 MW Β· withdrawn
- Solar project GEN-2022-244, Foard CountySolar Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem