United States › Grid › Interconnection queues › Minnesota
SOLAR + STORAGE · MISOSolar + storage project J3002, Pine County
Solar + storage project J3002, Pine County is a 288 MW solar + storage request in interconnection study in the MISO interconnection queue, in Pine County, Minnesota, connecting to MINNESOTA POWER INC..
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3002
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MINNESOTA POWER INC.
- Connection point (POI)
- Arrowhead - Bear Creek (GRE) 230kV
- Location
- Pine County, Minnesota
- Technology
- Solar: 288 MW · Battery
- Total requested
- 288 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- August 2025
Location
Marker shows the centre of Pine County; the queue data does not give exact sites.
Other requests in Pine County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem