| Project | Capacity | Status |
|---|---|---|
| Solar project AI2-374, Bath County Solar |
20.6 MW | In study |
| Solar project AI2-415, Butler County Solar |
20.3 MW | In study |
| Replacing 20 MW of solar with storage; J1746 Other |
20.2 MW | In study |
| Somers Solar, LLC Solar · Somers Solar, LLC |
20.0 MW | In study |
| Solar + storage project T2-042, Millard County Solar + storage |
20.0 MW | In study |
| Concho Solar I Solar |
20.0 MW | Paused / redesign |
| Coal project GI-40, New Madrid County Coal |
20.0 MW | In study |
| Battery storage project G0734, Benton County Battery storage |
20.0 MW | In study |
| Momentum Gratz Battery storage |
20.0 MW | Paused / redesign |
| Solar project Q246, Yuma County Solar |
20.0 MW | Agreement signed |
| SunEast Skyline Solar LLC Solar · SunEast Skyline Solar LLC |
20.0 MW | In study |
| Cedar Creek Solar Solar |
20.0 MW | Paused / redesign |
| SunEast Flat Stone Solar LLC Solar · SED NY Holdings LLC |
20.0 MW | In study |
| Farmers Valley Solar Solar |
20.0 MW | Agreement signed |
| Solar + storage project T2-006, Tooele County Solar + storage · PacifiCorp |
20.0 MW | In study |
| Little Pond Solar Solar · Little Pond Solar, LLC |
20.0 MW | In study |
| Battery storage project AG2-380, Queen Anne's County Battery storage · Concho Solar I, LLC |
20.0 MW | In study |
| Missouri Avenue Battery Storage Project Battery storage · Calpine Mid-Atlantic Development, LLC |
20.0 MW | Agreement signed |
| Solar + storage project T2-009, Umatilla County Solar + storage |
20.0 MW | In study |
| Geothermal project Company RA, Pershing County Geothermal |
20.0 MW | In study |
| Hills Solar Solar · SunEast Hills Solar LLC |
20.0 MW | In study |
| Battery storage project AH2-049, Somerset County Battery storage |
20.0 MW | In study |
| Mountain Holly Solar |
20.0 MW | Paused / redesign |
| Solar + storage project AI1-153, Dauphin County Solar + storage |
20.0 MW | In study |
| Hatchery Solar Solar · Hatchery Solar LLC |
20.0 MW | In study |
| Battery storage project AH2-048, Northampton County Battery storage |
20.0 MW | In study |
| Solar + storage project 340, Yellowstone County Solar + storage |
20.0 MW | In study |
| Solar project AH1-571 Solar · South Fork Solar, LLC |
20.0 MW | In study |
| Amelia Energy Facility Solar · Amelia Energy Facility, LLC |
20.0 MW | In study |
| Solar + storage project T2-039, Emery County Solar + storage |
20.0 MW | In study |
| Horsepen Branch Solar Solar + storage |
20.0 MW | Agreement signed |
| Battery storage project J1257, Tangipahoa Parish County Battery storage |
20.0 MW | Under construction |
| Battery storage project J1329, Washtenaw County Battery storage |
20.0 MW | Under construction |
| Reid Energy Center Battery storage · Reid Energy Center, LLC |
20.0 MW | In study |
| Flat Hill Solar Solar · Flat Hill Solar NY LLC. |
20.0 MW | In study |
| Calumet BESS Battery storage |
20.0 MW | Agreement signed |
| Solar project G1069, Harney County Solar |
20.0 MW | In study |
| Solar project J3065, Oceana County Solar |
20.0 MW | In study |
| Coal project GI-39, New Madrid County Coal |
20.0 MW | In study |
| Dog Corners Solar Solar · SunEast Dog Corners Solar LLC |
20.0 MW | In study |
| Solar project AH2-160, Highland County Solar |
20.0 MW | In study |
| Evergreen Energy Center Battery storage · Evergreen Energy Center, LLC |
20.0 MW | In study |
| Solar + storage project T2-044, Millard County Solar + storage |
20.0 MW | In study |
| Switchgrass Solar 1 Solar |
20.0 MW | Paused / redesign |
| Nutes Solar Solar |
20.0 MW | Agreement signed |
| Battery storage project AI2-010, Hanover County Battery storage |
20.0 MW | In study |
| Eaton OH Solar Solar |
20.0 MW | Agreement signed |
| Solar + storage project T2-045, Millard County Solar + storage |
20.0 MW | In study |
| Franklin Solar Solar |
20.0 MW | Agreement signed |
| Reedy Creek Solar + storage |
20.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)