United States › Grid › Interconnection queues › Illinois

BATTERY STORAGE · PJM

Calumet BESS

Calumet BESS is a 20.0 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in Cook County, Illinois, connecting to ComEd.

Queue statusConsented
  1. PlanningQueued Oct 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-031
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Calumet
Location
Cook County, Illinois
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Active
Entered queue
28 October 2019
Proposed online date
December 2027

Location

Marker shows the centre of Cook County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Cook County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem