United States βΊ Grid βΊ Interconnection queues βΊ Illinois
BATTERY STORAGE Β· PJMBattery storage project AG1-298, Cook County
Battery storage project AG1-298, Cook County is a 500 MW battery storage request withdrawn in the PJM interconnection queue, in Cook County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedJan 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-298
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Developer
- Big Shoulders Storage LLC
- Connection point (POI)
- Calumet-Burnham 345 kV
- Location
- Cook County, Illinois
- Technology
- Battery: 500 MW
- Total requested
- 500 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 29 September 2020
- Proposed online date
- June 2023
- Withdrawn
- January 2025
Location
Marker shows the centre of Cook County; the queue data does not give exact sites.
Other requests in Cook County
- Calumet BESSBattery storage Β· 20.0 MW Β· agreement signed
- Riverbank EnergyBattery storage Β· 200 MW Β· in study
- Battery storage project AI1-155, Cook CountyBattery storage Β· 110 MW Β· in study
- Battery storage project AH1-673, Cook CountyBattery storage Β· 85.0 MW Β· in study
- Battery storage project AH2-205, Cook CountyBattery storage Β· 10.0 MW Β· in study
- Battery storage project AH2-206, Cook CountyBattery storage Β· 10.0 MW Β· in study
- River Energy CenterGas Β· 27.0 MW Β· built
- City SolarSolar Β· 9.0 MW Β· built
- Gas project AC1-067, Cook CountyGas Β· 1,254 MW Β· withdrawn
- Southeast Chicago Energy Project (aka SCEP)Gas Β· 296 MW Β· withdrawn
- Gas project J648, Cook CountyGas Β· 296 MW Β· withdrawn
- Battery storage project J3008, Cook CountyBattery storage Β· 270 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem