SOLAR · ISO-NE

Nutes Solar

Nutes Solar is a 20.0 MW solar request with a signed interconnection agreement in the ISO-NE interconnection queue, in Strafford County, New Hampshire.

Queue statusConsented
  1. PlanningQueued May 2021 (completed)
  2. ConsentedJan 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1136
Grid region
ISO-NE (New England)
Connection point (POI)
43°23'7.50"N, 71° 1'23.45"W, Direct Tap, Circuit #3174 34.5 kV
Location
Strafford County, New Hampshire
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
20 May 2021
Agreement signed
9 January 2025
Proposed online date
May 2026

Location

Marker shows the centre of Strafford County; the queue data does not give exact sites.

Power plants in New Hampshire · Transmission lines in New Hampshire