United States › Grid › Interconnection queues › New York
SOLAR · NYISOSunEast Skyline Solar LLC
SunEast Skyline Solar LLC is a 20.0 MW solar request in interconnection study in the NYISO interconnection queue, in Oneida County, New York, connecting to NM-NG.
Queue statusIn planning
- PlanningQueued Sep 2017 (current stage)
- ConsentedAug 2020 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 670
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- SunEast Skyline Solar LLC
- Connection point (POI)
- Campus Rd - Clinton 46kV
- Location
- Oneida County, New York
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- FES, SIS, FS
- Queue status
- Active
- Entered queue
- 21 September 2017
- Agreement signed
- 13 August 2020
- Proposed online date
- April 2028
Location
Marker shows the centre of Oneida County; the queue data does not give exact sites.
Other requests in Oneida County
- SunEast Flat Stone Solar LLCSolar · 20.0 MW · in study
- CommodoreBattery storage · 1,200 MW · withdrawn
- Marcy BESS 3Battery storage · 435 MW · withdrawn
- Snowy Knoll Wind ProjectWind + storage · 350 MW · withdrawn
- Field Day SolarSolar + storage · 300 MW · withdrawn
- Verona Solar Energy Center IISolar · 250 MW · withdrawn
- Verona Solar Energy Center ISolar · 250 MW · withdrawn
- North CreekSolar + storage · 200 MW · withdrawn
- Verona Solar ISolar · 199 MW · withdrawn
- Marcy BESS 2Battery storage · 195 MW · withdrawn
- Alder Creek SolarSolar · 165 MW · withdrawn
- Kce NY 36 LLCBattery storage · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem