United States › Grid › Interconnection queues › New York
WIND + STORAGE · NYISOSnowy Knoll Wind Project
Snowy Knoll Wind Project is a 350 MW wind + storage request withdrawn in the NYISO interconnection queue, in Oneida County, New York, connecting to NYPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-221-003
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Snowy Knoll Wind Project, LLC
- Connection point (POI)
- Edic - Fraser 345kV
- Location
- Oneida County, New York
- Technology
- Wind: 350 MW · Battery
- Total requested
- 350 MW
- Queue status
- Withdrawn
- Entered queue
- 20 September 2024
Location
Marker shows the centre of Oneida County; the queue data does not give exact sites.
Other requests in Oneida County
- SunEast Skyline Solar LLCSolar · 20.0 MW · in study
- SunEast Flat Stone Solar LLCSolar · 20.0 MW · in study
- CommodoreBattery storage · 1,200 MW · withdrawn
- Marcy BESS 3Battery storage · 435 MW · withdrawn
- Field Day SolarSolar + storage · 300 MW · withdrawn
- Verona Solar Energy Center IISolar · 250 MW · withdrawn
- Verona Solar Energy Center ISolar · 250 MW · withdrawn
- North CreekSolar + storage · 200 MW · withdrawn
- Verona Solar ISolar · 199 MW · withdrawn
- Marcy BESS 2Battery storage · 195 MW · withdrawn
- Alder Creek SolarSolar · 165 MW · withdrawn
- Kce NY 36 LLCBattery storage · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem