United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 103

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 103 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J986, Wood County
Solar
150 MWAgreement signed Wood, WIMISO Mar 20182023
Solar project J1750, Marquette County
Solar
150 MWUnder construction Marquette, MIMISO Apr 2022target 2026
Solar project J1744, Cumberland County
Solar
150 MWIn study Cumberland, ILMISO Apr 2022target 2027
Cannibal Draw Solar
Solar + storage · Cannibal Draw Solar, LLC
150 MWAgreement signed Glasscock, TXERCOT Jul 2024target 2028
Solar project J1651, Logan County
Solar
150 MWIn study Logan, ILMISO Jun 2020target 2023
Riverstone Solar
Solar
150 MWAgreement signed Buckingham, VAPJM Sep 2018target 2027
Solar project 278, Williamsburg County
Solar
150 MWIn study Williamsburg, SCSoutheast Jun 2024target 2028
Gas project AH1-715, Union County
Gas · Parkway Generation Operating LLC
149 MWIn study Union, NJPJM Apr 2025
Pilesgrove Solar Project
Solar
149 MWPaused / redesign Salem, NJPJM Sep 2018target 2027
Maroon Solar
Solar
149 MWPaused / redesign Culpeper, VAPJM Sep 2018target 2027
Solar project J818, Jefferson County
Solar
149 MWUnder construction Jefferson, WIMISO Jun 2017target 2022
Solar project 636, Elmore County
Solar · Soles Rest Solar LLC
149 MWAgreement signed Elmore, IDWest Feb 2022target 2028
Enclave Solar Energy Center
Solar
149 MWPaused / redesign Sussex, VAPJM Jan 2019target 2027
Surplus; J806
Other
149 MWIn study Calhoun, MIMISO target 2026
Solar project J3679, Laporte County
Solar
149 MWIn study Laporte, INMISO Apr 2024target 2028
Ponferrada Solar
Solar · Karol Solar VI
149 MWIn study Navarro, TXERCOT Oct 2024target 2029
Rogers Draw BESS
Battery storage · ROGERS DRAW ENERGY STORAGE, LLC
149 MWAgreement signed Gillespie, TXERCOT Jan 2023target 2026
La Casa Wind
Onshore wind · LA CASA WIND, LLC
148 MWAgreement signed Stephens, TXERCOT Dec 2018target 2026
Cosper Solar
Solar · Gransolar Texas Twenty LLC
148 MWAgreement signed Bell, TXERCOT Jan 2023target 2027
Solar project J1752, Portage County
Solar
148 MWUnder construction Portage, WIMISO May 2022target 2026
Solar + storage project AI2-445, Tucker County
Solar + storage
148 MWIn study Tucker, WVPJM Mar 2023target 2026
Solar project GEN-2018-079, Craig County
Solar
148 MWAgreement signed Craig, OKSPP Nov 2018target 2029
Galaxy Solar
Solar + storage · Galaxy Solar, LLC
148 MWIn study Ellis, TXERCOT Mar 2024target 2028
Rain Lily Solar 1
Solar + storage · Rain Lily Solar 1 LLC
148 MWIn study Hood, TXERCOT Feb 2025target 2028
High Chaparral Solar 138kV
Solar · High Chaparral Solar Project, LLC
148 MWPaused / redesign Brazoria, TXERCOT Jan 2021target 2023
Onshore wind project GEN-2016-102, Pontotoc County
Onshore wind
148 MWAgreement signed Pontotoc, OKSPP Nov 20162025
John Bull BESS
Battery storage · BRP BLUE TOPAZ 13, LLC
147 MWIn study Nueces, TXERCOT Jul 2023target 2028
Onshore wind project J1755, Bureau County
Onshore wind
147 MWIn study Bureau, ILMISO Jun 2020target 2025
Solar project J2861, Mower County
Solar
147 MWIn study Mower, MNMISO Sep 2022target 2029
Onshore wind project AG2-062, Grant County
Onshore wind · Catamount Wind LLC
147 MWIn study Grant, WVPJM Feb 2025target 2022
Chisme Solar
Solar + storage · Blue Heron Solar, LLC
147 MWIn study Brown, TXERCOT Jan 2023target 2027
Solar project 305, Fayette County
Solar
147 MWAgreement signed Fayette, TNSoutheast Nov 2016target 2026
Prattsburgh Wind Farm
Onshore wind · Prattsburgh Wind, LLC
147 MWIn study Steuben, NYNYISO Feb 2019target 2027
Onshore wind project J3754, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Onshore wind project J3755, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Neal Solar
Solar + storage · CH Neal Solar LLC
147 MWIn study Wharton, TXERCOT May 2025target 2029
Dundee West Wind
Onshore wind · Felix 2, LLC
146 MWAgreement signed Wilbarger, TXERCOT Jan 2023target 2027
Wensowitch Solar
Solar · Greenalia Solar Power Wensowitch LLC
146 MWIn study Navarro, TXERCOT Jan 2022target 2028
Battery storage project J1354, Decatur County
Battery storage
146 MWAgreement signed Decatur, INMISO Apr 2019target 2025
Chisme Storage
Solar + storage · Blue Heron Solar, LLC
146 MWIn study Brown, TXERCOT Jan 2023target 2027
Onshore wind project J4054, Saginaw County
Onshore wind
146 MWIn study Saginaw, MIMISO Sep 2025target 2030
Solar project J3761, Ogemaw County
Solar
146 MWIn study Ogemaw, MIMISO Apr 2024target 2027
Moonstone Solar Project
Solar · Moon Stone Solar Farm, LLC
146 MWAgreement signed Wilson, TXERCOT Oct 2021target 2029
Solar project AH2-085, Dekalb County
Solar
145 MWIn study Dekalb, ILPJM Jan 2022target 2026
Solar project GEN-2022-065, Edwards County
Solar
145 MWIn study Edwards, KSSPP Jul 2022target 2027
Other project PP00034, Lee County
Other
145 MWIn study Lee, SCSoutheast Jul 2025target 2029
Segs Expansion 2 Hybrid
Solar + storage
145 MWAgreement signed San Bernardino, CACAISO Apr 2020target 2026
Kensington Solar
Solar
145 MWPaused / redesign Columbiana, OHPJM Mar 2019target 2026
Other project Q548, Pinal County
Other
145 MWIn study Pinal, AZWest Apr 2024target 2027
Seven Springs Solar
Solar + storage · Hancock Springs, LLC
145 MWAgreement signed Lampasas, TXERCOT Sep 2023target 2028
Page 103 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)