United States › Grid › Interconnection queues › Tennessee
SOLAR · SOUTHEASTSolar project 305, Fayette County
Solar project 305, Fayette County is a 147 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Fayette County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusConsented
- PlanningQueued Nov 2016 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget May 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 305
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- Cordova-S. Jackson 161-kV TL
- Location
- Fayette County, Tennessee
- Technology
- Solar: 147 MW
- Total requested
- 147 MW
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 22 November 2016
- Proposed online date
- May 2026
Location
Marker shows the centre of Fayette County; the queue data does not give exact sites.
Other requests in Fayette County
- Gas project 25RSC-001, Fayette CountyGas · 692 MW · in study
- Other project 171, Fayette CountyOther · 640 MW · withdrawn
- Other project 170, Fayette CountyOther · 640 MW · withdrawn
- Other project 161, Fayette CountyOther · 550 MW · withdrawn
- Solar project 353, Fayette CountySolar · 340 MW · withdrawn
- Solar project 584, Fayette CountySolar · 165 MW · withdrawn
- Solar project 335, Fayette CountySolar · 132 MW · withdrawn
- Solar + storage project 570, Fayette CountySolar + storage · 100 MW · withdrawn
- Solar project 495, Fayette CountySolar · 70.0 MW · withdrawn
- Solar project 481, Fayette CountySolar · 60.0 MW · withdrawn
- Solar project 346, Fayette CountySolar · 50.0 MW · withdrawn
- Solar + storage project 581, Fayette CountySolar + storage · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem