United States › Grid › Interconnection queues › Oklahoma

SOLAR · SPP

Solar project GEN-2018-079, Craig County

Solar project GEN-2018-079, Craig County is a 148 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Craig County, Oklahoma, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Nov 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-079
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Farmland-Delaware 138kV line
Location
Craig County, Oklahoma
Technology
Solar: 148 MW
Total requested
148 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
18 November 2018
Proposed online date
December 2029

Location

Marker shows the centre of Craig County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Craig County