United States › Grid › Interconnection queues › Oklahoma
SOLAR · SPPSolar project GEN-2018-079, Craig County
Solar project GEN-2018-079, Craig County is a 148 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Craig County, Oklahoma, connecting to AEP.
Queue statusConsented
- PlanningQueued Nov 2018 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2018-079
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Farmland-Delaware 138kV line
- Location
- Craig County, Oklahoma
- Technology
- Solar: 148 MW
- Total requested
- 148 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 18 November 2018
- Proposed online date
- December 2029
Location
Marker shows the centre of Craig County; the queue data does not give exact sites.
Other requests in Craig County
- Onshore wind project GI-123, Craig CountyOnshore wind · 300 MW · in study
- Onshore wind project GI-112, Craig CountyOnshore wind · 300 MW · withdrawn
- Solar + storage project GI-108, Craig CountySolar + storage · 250 MW · withdrawn
- Solar project GEN-2023-179, Craig CountySolar · 250 MW · withdrawn
- Solar project GEN-2024-146, Craig CountySolar · 250 MW · withdrawn
- Onshore wind project GEN-2024-238, Craig CountyOnshore wind · 200 MW · withdrawn
- Solar project GEN-2018-080, Craig CountySolar · 200 MW · withdrawn
- Solar + storage project GEN-2023-136, Craig CountySolar + storage · 150 MW · withdrawn
- Onshore wind project GEN-2013-009, Craig CountyOnshore wind · 100 MW · withdrawn
- Solar project GEN-2024-160, Craig CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem