United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project GI-108, Craig County

Solar + storage project GI-108, Craig County is a 250 MW solar + storage request withdrawn in the Southeast interconnection queue, in Craig County, Oklahoma, connecting to Associated Electric Cooperative, Incorporated.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-108
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Associated Electric Cooperative, Incorporated
Connection point (POI)
Sportsman-Blackberry 345 kV line
Location
Craig County, Oklahoma
Technology
Solar: 250 MW Β· Battery
Total requested
250 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
30 August 2022
Proposed online date
December 2025

Location

Marker shows the centre of Craig County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Craig County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem