🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

ONSHORE WIND · SOUTHEAST

Onshore wind project GI-123, Craig County

Onshore wind project GI-123, Craig County is a 300 MW onshore wind request in interconnection study in the Southeast interconnection queue, in Craig County, Oklahoma, connecting to Associated Electric Cooperative, Incorporated.

Queue statusIn planning
  1. PlanningQueued Sep 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-123
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Associated Electric Cooperative, Incorporated
Connection point (POI)
Sportsman-Blackberry 345 kV line
Location
Craig County, Oklahoma
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Active
Entered queue
3 September 2024
Proposed online date
December 2027

Location

Marker shows the centre of Craig County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Craig County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem