Solar project J818, Jefferson County

Solar project J818, Jefferson County is a 149 MW solar request under construction in the MISO interconnection queue, in Jefferson County, Wisconsin, connecting to American Transmission Co..

Queue statusUnder construction
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedMay 2020 (completed)
  3. Construction (current stage)
  4. OperatingTarget Apr 2022 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J818
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Jefferson 138kV Substation
Location
Jefferson County, Wisconsin
Technology
Solar: 149 MW
Total requested
149 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
16 June 2017
Agreement signed
6 May 2020
Proposed online date
April 2022

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.