United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J1154, Jefferson County
Solar project J1154, Jefferson County is a 75.0 MW solar request under construction in the MISO interconnection queue, in Jefferson County, Wisconsin, connecting to American Transmission Co..
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedMay 2021 (completed)
- Construction (current stage)
- OperatingApr 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1154
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Jefferson 138 kV Substation
- Location
- Jefferson County, Wisconsin
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 19 May 2021
- Proposed online date
- May 2023
- Came online
- April 2024
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Other requests in Jefferson County
- Solar project J818, Jefferson CountySolar · 149 MW · under construction
- Solar project J4101, Jefferson CountySolar · 71.0 MW · in study
- Gas project J174, Jefferson CountyGas · 43.8 MW · built
- Gas project G550, Jefferson CountyGas · 24.0 MW · built
- Solar project J1053, Jefferson CountySolar · 300 MW · withdrawn
- Solar project J1497, Jefferson CountySolar · 125 MW · withdrawn
- Battery storage project J1051, Jefferson CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem