BATTERY STORAGE · ERCOT

Rogers Draw BESS

Rogers Draw BESS is a 149 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Gillespie County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2023 (completed)
  2. ConsentedFeb 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0514
Grid region
ERCOT (Texas)
Developer
ROGERS DRAW ENERGY STORAGE, LLC
Connection point (POI)
7751 Headwaters substation 138kV
Location
Gillespie County, Texas
Technology
Battery: 149 MW
Total requested
149 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
3 January 2023
Agreement signed
28 February 2024
Proposed online date
June 2026

Location

Marker shows the centre of Gillespie County; the queue data does not give exact sites.