Marshall Spring Storage

Marshall Spring Storage is a 150 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Gillespie County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2023 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0354
Grid region
ERCOT (Texas)
Developer
Marshall Springs Storage, LLC
Connection point (POI)
New POI station between 7132 L_GILLES8_1Y - 7126 L_FERGUS8_1Y 138kV line and 7132 L_GILLES8_1Y - 7128 L_HORSBA8_1Y 138kV line, then loop in both lines into the new POI station.
Location
Gillespie County, Texas
Technology
Battery: 150 MW · Battery
Total requested
150 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
20 February 2023
Agreement signed
26 December 2025
Proposed online date
July 2026

Location

Marker shows the centre of Gillespie County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Gillespie County