United States › Grid › Interconnection queues › Illinois

SOLAR · MISO

Solar project J1744, Cumberland County

Solar project J1744, Cumberland County is a 150 MW solar request in interconnection study in the MISO interconnection queue, in Cumberland County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Apr 2022 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1744
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Hutsonville - Neoga 138 kV
Location
Cumberland County, Illinois
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
5 April 2022
Agreement signed
4 December 2025
Proposed online date
June 2027
Withdrawn
July 2023

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem