United States βΊ Grid βΊ Interconnection queues βΊ Illinois
BATTERY STORAGE Β· MISOBattery storage project J2658, Cumberland County
Battery storage project J2658, Cumberland County is a 150 MW battery storage request withdrawn in the MISO interconnection queue, in Cumberland County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedMar 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2658
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- 7CASEY-7NEWTON 345kV
- Location
- Cumberland County, Illinois
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- May 2026
- Withdrawn
- March 2023
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Other requests in Cumberland County
- Surplus; Glacier MoraineOther Β· 360 MW Β· in study
- Solar project J2662, Cumberland CountySolar Β· 250 MW Β· in study
- Surplus; ShelbyOther Β· 150 MW Β· in study
- Solar project J1744, Cumberland CountySolar Β· 150 MW Β· in study
- Solar project J1204, Cumberland CountySolar Β· 199 MW Β· withdrawn
- Solar project J1771, Cumberland CountySolar Β· 197 MW Β· withdrawn
- Battery storage project J2660, Cumberland CountyBattery storage Β· 150 MW Β· withdrawn
- Solar project J2453, Cumberland CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem