United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMMaroon Solar
Maroon Solar is a 149 MW solar request suspended in the PJM interconnection queue, in Culpeper County, Virginia, connecting to Dominion.
Queue statusPaused / redesign
- PlanningQueued Sep 2018 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AE1-153
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Remington-Gordonsville 230 kV
- Location
- Culpeper County, Virginia
- Technology
- Solar: 149 MW
- Total requested
- 149 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 25 September 2018
- Proposed online date
- May 2027
Location
Marker shows the centre of Culpeper County; the queue data does not give exact sites.
Other requests in Culpeper County
- Greenwood SolarSolar Β· 100 MW Β· agreement signed
- Cricket SolarSolar Β· 60.0 MW Β· agreement signed
- Greenwood SolarSolar Β· 50.0 MW Β· agreement signed
- Cricket SolarSolar Β· 20.0 MW Β· agreement signed
- Solar project AH1-437, Culpeper CountySolar Β· 150 MW Β· withdrawn
- Solar project AC2-121, Culpeper CountySolar Β· 150 MW Β· withdrawn
- Solar project AC2-022, Culpeper CountySolar Β· 100 MW Β· withdrawn
- Solar project AC2-102, Culpeper CountySolar Β· 80.0 MW Β· withdrawn
- Battery storage project AG1-538, Culpeper CountyBattery storage Β· 75.0 MW Β· withdrawn
- Elkwood SolarSolar Β· 60.0 MW Β· withdrawn
- Battery storage project AE2-188, Culpeper CountyBattery storage Β· 40.0 MW Β· withdrawn
- Solar project AB2-052, Culpeper CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem