United States › Grid › Interconnection queues › Ohio
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Ohio — page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Carnation Solar |
58.0 MW | Agreement signed |
| Blossom Solar Solar |
56.0 MW | Agreement signed |
| Hardin Energy Center – Storage II Battery storage |
55.0 MW | Paused / redesign |
| Solar project AI1-151, Adams County Solar |
53.2 MW | In study |
| Clermont County Solar Project Battery storage |
52.2 MW | Paused / redesign |
| Scioty Solar Solar |
50.0 MW | Agreement signed |
| Timber Road Storage III Battery storage |
50.0 MW | Agreement signed |
| Juliet Energy Solar |
50.0 MW | Agreement signed |
| Palomino Solar Solar |
50.0 MW | Agreement signed |
| Hardin Energy Center – Storage I Battery storage |
50.0 MW | Paused / redesign |
| Pleasant Prairie Solar Energy Center Solar |
50.0 MW | Agreement signed |
| Cadence Energy Storage Battery storage |
50.0 MW | Paused / redesign |
| Paulding Storage II Battery storage · Paulding Wind Farm II LLC |
50.0 MW | In study |
| Solar + storage project AI2-030, Adams County Solar + storage |
50.0 MW | In study |
| Mark Center Solar Project Solar |
49.9 MW | Agreement signed |
| White Trillium Solar |
49.9 MW | Agreement signed |
| Solar + storage project AH2-408, Wood County Solar + storage |
49.9 MW | In study |
| Eaton OH Solar Solar |
49.9 MW | Agreement signed |
| Solar project AI1-091, Seneca County Solar |
49.9 MW | In study |
| Solar project AI1-092, Butler County Solar |
49.9 MW | In study |
| Solar project AH1-282, Morrow County Solar · Woodbury Solar, LLC |
49.9 MW | In study |
| Timber Road Solar Park III Solar |
49.9 MW | Agreement signed |
| Solar + storage project AI1-150, Butler County Solar + storage |
49.9 MW | In study |
| Solar project AF2-298, Montgomery County Solar |
49.9 MW | Agreement signed |
| Steubenville Solar Solar |
49.5 MW | Paused / redesign |
| Recreation Solar Solar |
49.5 MW | Paused / redesign |
| Solar project AH2-159, Highland County Solar |
49.0 MW | In study |
| Woodsdale Renewable Energy Center Solar |
49.0 MW | Agreement signed |
| Solar + storage project AH2-239, Trumbull County Solar + storage |
49.0 MW | In study |
| Great Bend Solar |
48.0 MW | Agreement signed |
| Solar + storage project AH2-346, Hancock County Solar + storage |
47.5 MW | In study |
| South Branch Solar Solar |
46.0 MW | Paused / redesign |
| Solar + storage project AH2-242, Montgomery County Solar + storage |
45.0 MW | In study |
| Solar + storage project AH2-344, Marion County Solar + storage |
45.0 MW | In study |
| Solar project AH2-166, Fulton County Solar |
45.0 MW | In study |
| Solar + storage project AH2-028, Pickaway County Solar + storage |
44.0 MW | In study |
| Solar project AI2-159, Miami County Solar |
43.5 MW | In study |
| Vinton Energy Storage Battery storage |
42.0 MW | Paused / redesign |
| Solar project AH2-156, Huron County Solar |
40.0 MW | In study |
| Solar project AG2-109, Huron County Solar · Rosemary Solar, LLC |
40.0 MW | In study |
| Solar project AH2-009, Morrow County Solar |
40.0 MW | In study |
| Hillclimber Solar Battery storage |
40.0 MW | Agreement signed |
| Woodstock Solar Solar |
40.0 MW | Paused / redesign |
| Henry County Solar Solar |
40.0 MW | Paused / redesign |
| Hillclimber Solar Solar |
38.5 MW | Agreement signed |
| Battery storage project AG2-290, Seneca County Battery storage · Chinchilla Solar LLC |
38.4 MW | In study |
| Solar project AH2-081, Fayette County Solar |
35.5 MW | In study |
| Solar project AI2-336, Harrison County Solar |
34.6 MW | In study |
| Solar project AH2-082, Fayette County Solar |
33.3 MW | In study |
| West Lorain Power Plant 345 kV Gas |
33.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)