United States › Grid › Interconnection queues › Ohio
SOLAR · PJMSolar project AI1-091, Seneca County
Solar project AI1-091, Seneca County is a 49.9 MW solar request in interconnection study in the PJM interconnection queue, in Seneca County, Ohio, connecting to AEP.
Queue statusIn planning
- PlanningQueued Aug 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-091
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Bascom 69 kV
- Location
- Seneca County, Ohio
- Technology
- Solar: 49.9 MW
- Total requested
- 49.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 4 August 2022
- Proposed online date
- July 2025
Location
Marker shows the centre of Seneca County; the queue data does not give exact sites.
Other requests in Seneca County
- Battery storage project AG2-289, Seneca CountyBattery storage · 66.6 MW · in study
- Battery storage project AG2-290, Seneca CountyBattery storage · 38.4 MW · in study
- Onshore wind project AD2-136, Seneca CountyOnshore wind · 360 MW · withdrawn
- Republic Wind LLCOnshore wind · 200 MW · withdrawn
- Onshore wind project AE2-174, Seneca CountyOnshore wind · 198 MW · withdrawn
- Onshore wind project AD2-191, Seneca CountyOnshore wind · 170 MW · withdrawn
- Seneca WindOnshore wind · 100 MW · withdrawn
- Seneca WindOnshore wind · 100 MW · withdrawn
- Solar + storage project AG2-465, Seneca CountySolar + storage · 79.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem