United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Scioty Solar

Scioty Solar is a 50.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Hardin County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Sep 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-554
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
South Kenton 138 kV
Location
Hardin County, Ohio
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
30 September 2020
Proposed online date
October 2027

Location

Marker shows the centre of Hardin County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Hardin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem