Hardin Energy Center is a 20.0 MW solar request built and operating in the PJM interconnection queue, in Hardin County, Ohio, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Aug 2009 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
V3-028
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
East Lima-Marysville 345kV
Location
Hardin County, Ohio
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
31 August 2009
Proposed online date
June 2021
Came online
September 2020

Location

Marker shows the centre of Hardin County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Hardin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem