BATTERY STORAGE · PJM

Hardin Energy Center – Storage II

Hardin Energy Center – Storage II is a 55.0 MW battery storage request suspended in the PJM interconnection queue, in Hardin County, Ohio, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE2-216
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Hardin Switch 345 kV
Location
Hardin County, Ohio
Technology
Battery: 55.0 MW
Total requested
55.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
21 March 2019
Proposed online date
December 2026

Location

Marker shows the centre of Hardin County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Hardin County