SOLAR + STORAGE · PJM

Solar + storage project AH2-408, Wood County

Solar + storage project AH2-408, Wood County is a 49.9 MW solar + storage request in interconnection study in the PJM interconnection queue, in Wood County, Ohio, connecting to ATSI.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-408
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Fostoria - Lemoyne 138 kV
Location
Wood County, Ohio
Technology
Solar: 49.9 MW · Battery
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
10 March 2022
Proposed online date
June 2025

Location

Marker shows the centre of Wood County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Wood County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem