BATTERY STORAGE Β· PJM

Troy Battery Storage

Troy Battery Storage is a 250 MW battery storage request withdrawn in the PJM interconnection queue, in Wood County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-565
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Developer
Troy Energy, LLC
Connection point (POI)
Lemoyne 345kV
Location
Wood County, Ohio
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
June 2025
Withdrawn
May 2025

Location

Marker shows the centre of Wood County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Wood County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem