SOLAR Β· PJMSteubenville Solar
Steubenville Solar is a 49.5 MW solar request suspended in the PJM interconnection queue, in Jefferson County, Ohio, connecting to AEP.
Queue statusPaused / redesign
- PlanningQueued Nov 2017 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AD2-014
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Steubenville 69 kV
- Location
- Jefferson County, Ohio
- Technology
- Solar: 49.5 MW
- Total requested
- 49.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 10 November 2017
- Proposed online date
- December 2027
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Other requests in Jefferson County
- Battery storage project AH2-126, Jefferson CountyBattery storage Β· 100 MW Β· in study
- Coal project G579, Jefferson CountyCoal Β· 50.0 MW Β· built
- Coal project G580, Jefferson CountyCoal Β· 50.0 MW Β· built
- Coal project R68, Jefferson CountyCoal Β· 1,940 MW Β· withdrawn
- Coal project I07, Jefferson CountyCoal Β· 1,860 MW Β· withdrawn
- Pike IslandHydro Β· 50.0 MW Β· withdrawn
- Hydro project T175, Jefferson CountyHydro Β· 11.0 MW Β· withdrawn
- Other project X2-053, Jefferson CountyOther Β· 6.4 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem