United States › Grid › Interconnection queues › Ohio

BATTERY STORAGE · PJM

Battery storage project AH2-126, Jefferson County

Battery storage project AH2-126, Jefferson County is a 100 MW battery storage request in interconnection study in the PJM interconnection queue, in Jefferson County, Ohio, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-126
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Tidd 138 kV
Location
Jefferson County, Ohio
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
25 February 2022
Proposed online date
October 2026

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem