United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Great Bend

Great Bend is a 48.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Meigs County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Oct 2016 (completed)
  2. ConsentedDec 2021 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AC1-082
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Ravenswood-Hemlock 69kV
Location
Meigs County, Ohio
Technology
Solar: 48.0 MW
Total requested
48.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
1 October 2016
Agreement signed
1 December 2021
Proposed online date
October 2025

Location

Marker shows the centre of Meigs County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Meigs County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem