🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kentucky

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Kentucky — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13421.5 GW
Active in queue21.5 GW134 requests
Agreement signed7,260 MW36 requests
Withdrawn33364.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

134 requests · page 2 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project LGE-GIS-2021-013, Hardin County
Battery storage
120 MWAgreement signed Hardin, KYSoutheast Mar 2021target 2028
Solar project 649, Muhlenberg County
Solar
119 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2033
Solar + storage project LGE-GIS-2021-018, Bath County
Solar + storage
110 MWPaused / redesign Bath, KYSoutheast May 2021target 2027
Summer Shade Solar
Solar + storage · Summer Shade Solar, LLC
106 MWAgreement signed Metcalfe, KYPJM Sep 2020target 2028
Solar project LGE-CS2025-013, Ballard County
Solar
100 MWIn study Ballard, KYSoutheast Dec 2025target 2028
Battery storage project AH2-125
Battery storage
100 MWIn study KYPJM Feb 2022target 2028
Solar + storage project LGE-GIS-2021-017, Mason County
Solar + storage
100 MWPaused / redesign Mason, KYSoutheast Apr 2021target 2026
Surplus; J1638
Battery storage
100 MWIn study Hancock, KYMISO Jan 2025target 2029
Solar project AH1-664, Fleming County
Solar · Hummingbird Energy LLC
100 MWIn study Fleming, KYPJM Feb 2025
Solar project J3165, Breckinridge County
Solar
100 MWIn study Breckinridge, KYMISO Sep 2022target 2025
Threeforks Energy Storage
Battery storage
100 MWAgreement signed Martin, KYPJM Sep 2019target 2028
Solar + storage project AI1-180
Solar + storage
100 MWIn study KYPJM Sep 2022target 2027
Solar project LGE-GIS-2021-019, Boyle County
Solar
100 MWPaused / redesign Boyle, KYSoutheast May 2021target 2027
Madison Solar 1
Solar · AEUG Madison Solar, LLC
100 MWIn study Madison, KYPJM Mar 2019target 2021
Solar project J2739, Ohio County
Solar
100 MWIn study Ohio, KYMISO Sep 2022target 2026
Solar project LGE-GIS-2019-025, Mercer County
Solar
99.0 MWAgreement signed Mercer, KYSoutheast May 2019target 2026
Solar project 642, Muhlenberg County
Solar
96.0 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2033
Solar project 609, Mccracken County
Solar
96.0 MWIn study Mccracken, KYSoutheast Feb 2024target 2027
Northern Bobwhite Solar
Solar
96.0 MWAgreement signed Marion, KYPJM Sep 2018target 2027
Gas project LGE-GIS-2024-006, Jefferson County
Gas
94.0 MWAgreement signed Jefferson, KYSoutheast May 2024target 2026
Solar project LGE-GIS-2017-002, Lyon County
Solar
86.0 MWAgreement signed Lyon, KYSoutheast Mar 2017target 2024
Solar project AH2-130
Solar
85.0 MWIn study KYPJM Feb 2022target 2026
Solar + storage project AI1-165, Green County
Solar + storage
85.0 MWIn study Green, KYPJM Sep 2022target 2026
Solar + storage project AI1-132, Washington County
Solar + storage
83.0 MWIn study Washington, KYPJM Sep 2022target 2029
Stonecrop Solar
Solar · CPV Stonecrop Solar, LLC
82.0 MWAgreement signed Hardin, KYPJM Sep 2020target 2029
Solar project AH1-239, Boone County
Solar · Clinton Solar, LLC
80.0 MWIn study Boone, KYPJM Mar 2025target 2024
Bright Mountain Solar
Solar
80.0 MWAgreement signed Perry, KYPJM Jul 2020target 2027
Solar project AH1-666, Fleming County
Solar · Fleming Solar, LLC
80.0 MWIn study Fleming, KYPJM Mar 2025
Solar project AH1-665, Fleming County
Solar · Hummingbird Energy LLC
80.0 MWIn study Fleming, KYPJM May 2025
Solar project AH2-002, Barren County
Solar
80.0 MWIn study Barren, KYPJM Oct 2021target 2024
Gas project LGE-GIS-2024-002, Hopkins County
Gas
75.0 MWAgreement signed Hopkins, KYSoutheast Feb 2024target 2027
Solar project 650, Muhlenberg County
Solar
72.0 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2029
Solar + storage project AH2-383, Fleming County
Solar + storage
70.0 MWIn study Fleming, KYPJM Mar 2022target 2027
Blue Moon Solar
Solar
70.0 MWAgreement signed Harrison, KYPJM Feb 2018target 2026
Solar project 388, Simpson County
Solar
69.0 MWAgreement signed Simpson, KYSoutheast Aug 2019target 2025
Solar + storage project AI1-079, Adair County
Solar + storage
64.8 MWIn study Adair, KYPJM Jul 2022target 2026
Solar + storage project AG2-424, Larue County
Solar + storage · Magnolia Solar and Grazing Farm LLC
63.3 MWIn study Larue, KYPJM Mar 2025target 2023
Mt Olive Creek Solar
Solar
60.0 MWAgreement signed Russell, KYPJM Jun 2019target 2026
Gas project 657, Muhlenberg County
Gas
60.0 MWIn study Muhlenberg, KYSoutheast Oct 2024target 2030
Horseshoe Bend Solar
Solar
60.0 MWAgreement signed Green, KYPJM Jul 2019target 2026
Solar project J1649, Mccracken County
Solar
60.0 MWIn study Mccracken, KYMISO Mar 2021target 2025
Flat Run Solar
Solar
55.0 MWAgreement signed Barren, KYPJM Aug 2019target 2026
Barrelhead
Solar · Barrelhead Solar, LLC
54.0 MWAgreement signed KYPJM Sep 2020target 2029
Solar project AG2-073, Madison County
Solar · SR Madison, LLC
53.0 MWIn study Madison, KYPJM Mar 2025target 2024
Solar + storage project AH2-076, Perry County
Solar + storage
52.5 MWIn study Perry, KYPJM Jan 2022target 2023
Solar project J1604, Henderson County
Solar
50.0 MWIn study Henderson, KYMISO Jul 2020target 2026
Pike County Solar
Solar
50.0 MWPaused / redesign Pike, KYPJM Oct 2016target 2028
Solar + storage project AI1-019
Solar + storage
50.0 MWIn study KYPJM Apr 2022target 2026
Solar + storage project AI1-133, Fleming County
Solar + storage
50.0 MWIn study Fleming, KYPJM Sep 2022target 2029
Pike County Solar
Solar
50.0 MWPaused / redesign Pike, KYPJM Oct 2016target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)