United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMBlue Moon Solar
Blue Moon Solar is a 70.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Harrison County, Kentucky, connecting to EKPC.
Queue statusConsented
- PlanningQueued Feb 2018 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AD2-048
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Cynthia-Headquarters 69 kV
- Location
- Harrison County, Kentucky
- Technology
- Solar: 70.0 MW
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 1 February 2018
- Proposed online date
- June 2026
Location
Marker shows the centre of Harrison County; the queue data does not give exact sites.
Other requests in Harrison County
- Bluebird SolarSolar · 80.0 MW · built
- Bluebird SolarSolar · 20.0 MW · built
- Solar project AC1-079, Harrison CountySolar · 80.0 MW · withdrawn
- Solar project AC2-069, Harrison CountySolar · 60.0 MW · withdrawn
- Solar project AD2-036, Harrison CountySolar · 60.0 MW · withdrawn
- Solar project LGE-GIS-2017-003, Harrison CountySolar · 35.0 MW · withdrawn
- Solar project LGE-GIS-2017-004, Harrison CountySolar · 25.0 MW · withdrawn
- Solar project LGE-GIS-2017-005, Harrison CountySolar · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem