United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR Β· PJMSolar project AC2-069, Harrison County
Solar project AC2-069, Harrison County is a 60.0 MW solar request withdrawn in the PJM interconnection queue, in Harrison County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2017 (completed)
- Withdrawn / abandonedSep 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC2-069
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Jacsonville-Renaker 138kV III
- Location
- Harrison County, Kentucky
- Technology
- Solar: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 27 February 2017
- Proposed online date
- June 2019
- Withdrawn
- September 2017
Location
Marker shows the centre of Harrison County; the queue data does not give exact sites.
Other requests in Harrison County
- Blue Moon SolarSolar Β· 70.0 MW Β· agreement signed
- Bluebird SolarSolar Β· 80.0 MW Β· built
- Bluebird SolarSolar Β· 20.0 MW Β· built
- Solar project AC1-079, Harrison CountySolar Β· 80.0 MW Β· withdrawn
- Solar project AD2-036, Harrison CountySolar Β· 60.0 MW Β· withdrawn
- Solar project LGE-GIS-2017-003, Harrison CountySolar Β· 35.0 MW Β· withdrawn
- Solar project LGE-GIS-2017-004, Harrison CountySolar Β· 25.0 MW Β· withdrawn
- Solar project LGE-GIS-2017-005, Harrison CountySolar Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem