United States › Grid › Interconnection queues › Kentucky
SOLAR + STORAGE · PJMSummer Shade Solar
Summer Shade Solar is a 106 MW solar + storage request with a signed interconnection agreement in the PJM interconnection queue, in Metcalfe County, Kentucky, connecting to EKPC.
Queue statusConsented
- PlanningQueued Sep 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AG1-341
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- Summer Shade Solar, LLC
- Connection point (POI)
- Summer Shade 161 kV
- Location
- Metcalfe County, Kentucky
- Technology
- Solar: 106 MW · Battery
- Total requested
- 106 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Active
- Entered queue
- 30 September 2020
- Proposed online date
- December 2028
Location
Marker shows the centre of Metcalfe County; the queue data does not give exact sites.
Other requests in Metcalfe County
- Glover Creek SolarSolar · 35.0 MW · built
- Glover Creek SolarSolar · 20.0 MW · built
- Other project 132, Metcalfe CountyOther · 640 MW · withdrawn
- Other project 57, Metcalfe CountyOther · 640 MW · withdrawn
- Solar project AG2-684, Metcalfe CountySolar · 331 MW · withdrawn
- Solar project AG2-094, Metcalfe CountySolar · 150 MW · withdrawn
- Solar project AH1-083, Metcalfe CountySolar · 100 MW · withdrawn
- Solar project AH1-081, Metcalfe CountySolar · 60.0 MW · withdrawn
- Solar + storage project AG2-598, Metcalfe CountySolar + storage · 50.0 MW · withdrawn
- Solar project AH1-082, Metcalfe CountySolar · 44.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem